As phase III expansion, Technopark is developing 92 acres of land in between the existing campus and the Second phase 86 acres. The Phase III will be developed by Technopark and an SPV Company as Special Economic Zone. In addition, land will also be allotted to IT/ITES Companies for construction of their own campuses. Special Economic Zone Status has already been granted for 27.5 acres of land. The 110KV sub-station is ready and have commenced distribution of power suppy for Phase-II Infosys buildings and temporary power required for phase III construction activities.
CURRENT STATUS :
* SEZ notification issued
* Contract for the 1 million sq..ft. state-of-the-art IT/ITES building awarded L & T. L & T has commenced work at site. The building is expected to be ready for occupation by August 2011. The building is designed by a consortium of Architects - Hafeez Contractor and Iyer & Mahesh.
* The land allotment process for IT/ITES Companies and IT infrastructure development companies is underway.
* Land development - compound wall, internal roads, etc. in progress
* Water supply and sewage treatment plant works in progress
FACT SHEET:
- Project area: 84 Acres
- On the main National Highway by-pass in between Technopark Phase I & II
- 9 Kms. from the Trivandrum International Airport
- Location: Adjacent to Technopark Campus, Near University of Kerala.
- Type of development: SEZ & nonSEZ
- Basic infrastructure- power, water, roads, telecom, datacom, water treatment plant
- Good access roads to the park.
OFFERINGS:
- Land under SEZ scheme for IT/ITES companies and developers
- 1 Million sqft Built-up space to be ready by 2011
WORKS IN PROGRESS
1). Construction of IT Building complex(1 million sqft).
Scheduled date of completion: 04/09/2011
Present Status
Dynamic Load Test in progress Grade Slab Concreting

- Piling works at building area is under progress using rotary rigs, truck mounted rigs and DMC rigs
2. Site Development, Construction of roads etc:
Present Status
- 71% of the earth filling work is under progress.
- Compound wall work is under progress at southern boundary near substation.
- Pipe line culvert work in progress near KSEB 5th Tower Point.
Pipe Culvert Work in progress Retaining Wall

3. Embankment protection work
Rubble Stocking for Gabion Work Gabion Mesh Stocking